Project managers use written correspondence to ensure their message is:

  1. Grammatically correct

  2. Memorable

  3. Clearly conveyed

  4. Delivered promptly

The correct answer is: Clearly conveyed

The emphasis on written correspondence in project management is primarily about ensuring that the message is clearly conveyed. Effective communication is critical in any project environment, as it minimizes the risk of misunderstandings and misinterpretations. This clarity helps team members, stakeholders, and other parties involved understand the objectives, requirements, and any necessary actions to be taken. While grammatical correctness, memorability, and prompt delivery are also important aspects of communication, they don't capture the overarching goal of written correspondence as clearly as the clarity of the message does. Grammatical correctness is essential to support clarity but it is a means to an end rather than the end itself. Similarly, while a memorable message can be beneficial, in the context of project management, clarity takes precedence, as it directly influences the effectiveness of the collaboration and the achievement of project goals. Prompt delivery of messages is important as well, but again, it is the clarity of the communication that ultimately determines its effectiveness in facilitating successful project outcomes.