Question: 1 / 205

In project management, what term is used for measuring results and implementing corrective action?

Coordination

Control

The term that refers to measuring results and implementing corrective action is 'Control.' In project management, control involves monitoring the project's progress against the established benchmarks and objectives to ensure that it remains on track. This process typically includes assessing project performance, identifying any variances from the plan, and taking necessary corrective actions to address those discrepancies.

Effective project control helps project managers maintain oversight and make informed decisions that align the project's outcomes with its goals. By focusing on control, project managers ensure that resources are utilized efficiently, risks are managed appropriately, and any deviations from the project plan can be promptly addressed, ensuring successful project delivery.

While coordination refers to the organization of different elements of a project to ensure they work together effectively, and synergy involves the collaborative efforts that result in a greater outcome than the sum of individual efforts, neither specifically encompasses the process of measuring and correcting results. Feedback, on the other hand, signifies the information received regarding performance but does not inherently involve the active implementation of corrective measures.

Synergy

Feedback